Best Practices for Temporary Heat and Drying (2025)

Field-tested practices to heat and dry small jobs safely and fast. Correct setpoints, equipment choices, safety, and finish-ready targets—without callbacks.

Best Practices for Temporary Heat and Drying (2025)

Introduction

Temporary heat and drying can make or break interior finish quality and schedule. Done right, you stabilize temperature and humidity, reduce drying times, and prevent callbacks. Done poorly, you trap moisture, create safety hazards, and delay finishes. This guide shows what to control, why it matters, and how to set up safe, effective temporary climate control on small jobs—so your paint, drywall, and flooring install once and last.

Table of Contents

Key Takeaways

  • Maintain indoor RH roughly 30–60% and 65–72°F for most finishes; aim 40–50% RH during wood acclimation (ASHRAE comfort guidance).
  • OSHA’s permissible exposure limit for CO is 50 ppm as an 8‑hour TWA; use electric or indirect-fired units indoors and CO monitoring when combustion is nearby.
  • A 50‑pint dehumidifier removes about 6.25 gallons per day at AHAM conditions; size units to room volume and moisture load.
  • For hardwood, the NWFA allows wood‑to‑subfloor moisture differences of less than 4% (strip) or 2% (wide plank) before install.
  • Heater sizing shortcut: BTU/hr ≈ 1.1 × CFM × ΔT; 1 kW equals 3,412 BTU/hr for quick electric-to-BTU conversions.

Why Heat and Drying Matter on Small Jobs

Problem

Small residential projects often rely on building HVAC that’s off or not commissioned. Cold, damp interiors slow drywall and paint curing, cause joint compound shrinkage cracks, and lead to flooring failures. Even a 10°F temperature drop can double waterborne paint recoat times per typical manufacturer data. Uncontrolled RH above 65% can keep gypsum wet for days and warp trim.

Solution

Control two variables from day one of finishes: temperature and humidity. Target 65–72°F and 40–50% RH for most interior finishes. Plan temporary heat and dehumidification together; heat alone won’t remove moisture—it just increases air’s capacity to hold it. Vent moisture out or condense it out with dehumidifiers.

Example

A two‑bath refresh in November had interior temps at 52°F/70% RH. After setting two 5 kW electric heaters and a 70‑pint dehumidifier, the crew stabilized at 68°F/48% RH within 6 hours and completed two paint coats in one day with no flashing or extended recoat times.

Choose the Right Equipment

Problem

Using the wrong heater or dehumidifier risks moisture buildup, CO exposure, or soot contamination of finishes. Direct‑fired “torpedo” heaters add water vapor and combustion byproducts to the space—bad news for paint and drywall.

Solution

Match equipment to space, power availability, and safety constraints.

Equipment TypeUse CaseProsWatchouts
Electric resistance heaters (5–10 kW)Finished interiors with powerClean heat, no added moistureRequires adequate amperage and GFCI protection
Indirect‑fired diesel/propane (ducted)Larger spaces where combustion stays outsideHigh BTU, keeps byproducts outdoorsRequires ducting, fuel logistics
Direct‑fired heaters (propane/kerosene)Ventilated shells onlyHigh output, low costAdds moisture and CO; not for finished spaces
Refrigerant dehumidifier (50–120 pints/day)60°F+ spacesEfficient water removalPerformance drops below 55°F
Desiccant dehumidifierCool or unheated spacesWorks at low tempsHigher operating cost

Sizing Basics

  • Heat: BTU/hr ≈ 1.1 × CFM × ΔT. If you can’t measure CFM, start with 15–20 BTU/hr per square foot in moderately insulated spaces for a 20–25°F lift, then verify with a thermometer.
  • Conversion: 1 kW = 3,412 BTU/hr. A 5 kW heater delivers about 17,000 BTU/hr.
  • Moisture: A 50‑pint unit (AHAM) removes ~6.25 gallons/day. Use one 50–70 pint unit per 600–900 sq ft of active drying area, then adjust to actual RH.

Example

A 900 sq ft apartment (8 ft ceilings) needed a 20°F lift. Estimated 18,000–25,000 BTU/hr plus one 70‑pint dehumidifier. The crew used a 7.5 kW electric heater (≈25,600 BTU/hr) and hit 68°F within 90 minutes; RH dropped from 62% to 46% in 24 hours.

Setpoints, Monitoring, and Safety

Problem

Heaters left unattended, fuel indoors, and missing CO detectors are common safety failures. Without monitoring, you can overshoot or drift out of spec overnight.

Solution

Set clear targets, monitor with data logs, and follow safety standards.

Targets and Tracking

  • Temperature: 65–72°F for most waterborne coatings and drywall.
  • Humidity: Maintain 40–50% RH during finish stages; keep under 60% to avoid slowdowns.
  • Instruments: Use a calibrated thermo‑hygrometer per room. Log readings morning, mid‑day, and end‑of‑day. A $40 CO detector with digital ppm display is cheap insurance.

Safety Essentials

  • Combustion safety: OSHA’s CO PEL is 50 ppm (8‑hour TWA). Keep combustion equipment outside the finish space (indirect‑fired) and duct in warm air, or use electric.
  • Clearances: Respect manufacturer‑listed clearances to combustibles; keep heaters off dust and away from solvents.
  • Power: Use GFCI‑protected circuits for portable electric heaters and dehumidifiers. Avoid daisy‑chaining extension cords; use appropriately rated cables.
  • Fuel: Store LP cylinders per NFPA 58 and keep out of living areas. Never refuel indoors.

Example

On a townhouse repaint, CO spiked to 18 ppm when a direct‑fired heater was briefly used in a closed room. The team moved to an indirect‑fired unit outdoors with ducting and added a second electric heater for spot heat. CO held at 0–2 ppm, and RH stabilized at 45%.

Finish-Ready Targets and Scheduling

Problem

Installing finishes before substrates are conditioned leads to joints telegraphing, paint flashing, cupped flooring, and adhesive failures. Rushing costs more than waiting a day.

Solution

Sequence by substrate readiness, not calendar dates. Use manufacturer thresholds and trade standards.

Drywall and Paint

  • Joint compound: Sand and recoat only when fully dry to the core; at 68°F/50% RH, plan roughly overnight per coat—longer at lower temp/higher RH.
  • Paint: Many acrylics allow recoat in 2–4 hours at 70°F/50% RH; colder or wetter conditions can double this. Ventilate or dehumidify to stay on spec.

Flooring and Woodwork

  • Hardwood (NWFA): Wood MC typically 6–9% indoors; wood-to-subfloor MC difference less than 4% for strip, 2% for plank before install.
  • Resilient flooring: Follow adhesive RH limits; many products specify slab RH under 75–85% (ASTM F2170) and temperature 65–85°F for 48 hours before and after.
  • Trim: Acclimate in the space for 48–72 hours at target temp/RH before install.

Example

A crew held a kitchen at 70°F/45% RH for three days prior to LVP install. Slab RH measured 75%, within adhesive spec. Result: zero seam peaking or adhesive bleed; installer finished a day early due to reduced open time variability.

Pricing and Client Communication

Problem

Temporary heat and drying are often invisible line items, leading to pushback or unpaid costs. Vague descriptions cause disputes when electrical upgrades or fuel runs are needed.

Solution

Quote temporary climate control as a defined scope with measurable targets and responsibilities.

What to Include

  • Setpoints: “Maintain 68°F ±3° and 45–55% RH during drywall, paint, and flooring.”
  • Equipment: “One 7.5 kW electric heater, one 70‑pint dehumidifier; indirect‑fired unit if ambient is less than 40°F.”
  • Power/fuel: “Client to provide two dedicated 30A circuits, or add-on cost for temporary power. Fuel billed at cost plus handling.”
  • Monitoring: “Daily logs of temp/RH provided upon request.”
  • Exclusions: “Not responsible for building HVAC commissioning; pricing assumes exterior closures in place.”

Using Donizo to Speed Approvals

Capture site conditions with voice and photos and generate a clear, branded proposal in minutes using Donizo. Clients can review in the portal and accept with e‑signature. When accepted, convert to an invoice in one click and track payments on paid plans. Many contractors find this saves 1–2 hours per small job and reduces back‑and‑forth.

Example

A bathroom remodel added “Temporary Heat and Drying” as an optional line. The client e‑signed the add‑on the same day via Donizo’s proposal link. The crew documented setpoints and billed fuel weekly—no disputes at closeout.

Frequently Asked Questions

What Heater Type Is Best for Finished Interiors?

Use electric resistance or indirect‑fired heaters. Keep combustion and exhaust outdoors with ducted warm air if using indirect‑fired. Avoid direct‑fired units in finished spaces—they add moisture and combustion byproducts.

How Do I Size Dehumidifiers?

Start with one 50–70 pint unit per 600–900 sq ft of active drying area at 65–70°F. Verify with a hygrometer. If RH stays above 55% after 6–8 hours, add capacity or switch to desiccant in cooler spaces.

What Are Safe CO Levels on Site?

Aim for 0–9 ppm background. OSHA’s permissible exposure limit is 50 ppm as an 8‑hour TWA, but you should take action long before that. Use electric or indirect‑fired equipment and a CO monitor whenever combustion equipment is on site.

How Long Should Wood Acclimate Before Install?

Typically 48–72 hours at target temperature and humidity with packaging opened and air circulation. Confirm wood and subfloor moisture are within NWFA differentials: less than 4% for strip, less than 2% for plank.

Do I Need to Run Equipment After Finishes Are Installed?

Yes. Maintain specified temp/RH 24–48 hours after paint and flooring per manufacturer instructions to ensure cure and adhesive performance.

Conclusion

Temporary heat and drying are controllable variables that protect finish quality and schedule. Set clear targets (around 68°F and 40–50% RH), choose the right equipment for the space, monitor daily, and schedule by substrate readiness—not the calendar. To get fast client approval, use Donizo to capture site details by voice, generate a clear proposal with climate control as a defined scope, collect e‑signatures, and convert approved work to invoices in one click. That keeps jobs moving and margins protected.