Introduction
If your jobs finish late, your margins are probably leaking through productivity. Not because crews are lazy—because rates aren’t defined, tracked, or used to plan. Productivity rates are simply how fast your crew turns labor hours into installed work. When you know them, you can schedule accurately, price confidently, and spot problems early instead of at the punch list. This guide walks you through what to track, how to set baselines, and how to use rates in the real world. No fancy systems required, just consistent units, simple tallying, and clear assumptions. You’ll get sample benchmarks, a quick tracking method, and a way to improve week by week without slowing production.
Table of Contents
Key Takeaways
- Productivity rates are units per labor-hour (or hours per unit) for a specific crew under defined conditions.
- Consistent units and daily tallies are more valuable than complex software you never use.
- Contractors commonly report 30–60 minutes lost per day to material fetches—staging fixes a lot of it.
- Many teams see 10–20% variance between planned and actual when drawings are unclear; early clarifications help.
- Use your rates to set durations and price work; document assumptions in your proposal so everyone plays by the same rules.
What Are Productivity Rates?
Productivity rates quantify output: either units per labor-hour (UPH) or hours per unit (HPU). The problem is most schedules and bids are built on gut feel. That’s why jobs slip.
Solution
Define rates by crew and condition. Example: “2-person crew hangs 350–450 square feet of drywall per labor-hour in open areas, 200–300 in tight kitchens.” Once the conditions are clear, you can predict time and cost reliably.
Example
If your rate for setting 2x4 wall studs is 0.08 hours per stud (about 12.5 studs per labor-hour) in open framing, a wall with 400 studs needs roughly 32 labor-hours. With a 3-person crew, that’s about 1.1 crew-days under similar conditions. If the area is tight or material is on level 3 with no elevator, you’ll need to adjust upward.
Step 1: Define Crews, Units, and Conditions
Many contractors struggle because their rates are vague. “We frame fast” isn’t a rate. You need a unit, a crew, and the job conditions.
Choose Measurable Units
- Framing: studs installed, linear feet of plates, square feet of sheathing
- Drywall: square feet hung or finished to level
- Paint: square feet per coat, or doors/frames per hour
- Concrete: cubic yards placed and finished, or square feet of formed area
- Tile: square feet set, or linear feet of base
Pick one unit per task so you can compare apples to apples.
Document Conditions
Capture the stuff that changes output:
- Access: ground level vs. stairs, lift availability
- Layout: open new build vs. remodel with occupied areas
- Height: standard 8–9 feet vs. high ceilings
- Material handling: staged at point-of-use vs. pallets at curb
- Weather: exterior work during wet/cold seasons
In general, exterior work in poor weather can reduce output by 15–25%. Tight remodels often run a third slower than open new builds.
Include Crew Composition
Rates are crew-specific. A 2-person finish crew performs differently than a 4-person framing crew with a dedicated material handler. Note the mix.
Step 2: Build Realistic Baselines
A common mistake is copying rates from a book without field validation. Good baselines come from your jobs with your people and your tools.
Start With Past Jobs
Grab three recent, similar projects. For each task, note total units installed and total labor-hours. Divide to get UPH or HPU. This gets you in the ballpark.
Use Short Studies
For the next two weeks, run quick spot checks: 2–4 hour windows where the foreman logs units installed and hours worked. Five samples per task commonly give you a usable baseline without killing productivity.
Adjust for Known Factors
- Material staging at point-of-use commonly saves 10–15% on handling time.
- Cluttered drawings and late RFIs often create 10–20% productivity swings.
- In general, long travel paths (parking to work area) can steal 15–30 minutes at start, lunch, and end of day.
Starter Benchmarks (Sanity Checks)
These are general starting points. Your rates will vary with region, crew skill, tools, and codes.
| Task | Baseline Unit | Typical Crew | Starting Benchmark |
|---|
| 2x4 Wall Studs (open) | studs installed | 3-person | 10–14 studs per labor-hour |
| Drywall Hang (open areas) | square feet | 2-person | 350–450 sq ft per labor-hour |
| Paint (walls, one coat) | square feet | 2-person | 600–900 sq ft per labor-hour |
| Tile Set (floor, straight lay) | square feet | 2-person | 40–70 sq ft per labor-hour |
Example
A two-person painting crew covers 750 sq ft per labor-hour on open walls in a new build. On a remodel with occupied spaces and frequent breaks for tenants, they drop to 500–600. You’d set two separate baseline rates and use the right one when bidding.
Step 3: Track in the Field Without Slowing Work
If tracking becomes a burden, it won’t happen. Keep it simple and consistent.
Daily Tally Method
- Foreman logs units installed (e.g., 1,800 sq ft drywall hung) and labor-hours (e.g., 16 crew-hours).
- Note any special conditions that day: lift down, change order, weather, material delay.
- Do this once at lunch and once at day’s end. Two minutes each time.
Many crews that adopt daily tallies report they cut variance by 5–10% within a month because issues surface early.
Use Voice Notes
Foremen are busy. A quick voice memo like “Day 3, north wing, drywall hung 1,600 sq ft, 14 hours, lift was shared 2 hours” is enough. Transcribe later.
If you’re pricing a change order or a small job from the field, use Donizo to turn a quick voice description and photos into a clean proposal fast. Clear scope and assumptions reduce the back-and-forth and keep work moving.
Example
Siding crew: 1,200 sq ft installed, 24 labor-hours. That’s 50 sq ft per labor-hour. Normal for this crew is 65–75. The note says “material staged 150 feet away.” Tomorrow, the GC stages at the scaffold—output jumps to 70. Problem found and fixed within 24 hours.
Step 4: Diagnose Bottlenecks and Improve
Productivity dips usually come from a short list of causes. Fix the cause, not the symptom.
Material Flow
Problem: Too many trips for fasteners, cuts, or panels.
Solution: Point-of-use staging, cut stations, and a dedicated material handler on heavy days.
Example: Contractors commonly report 30–60 minutes lost per day per crew to material runs. A rolling cart with pre-sorted hardware and a cut station at each floor often recovers most of it.
Problem: Unclear drawings, missing dimensions, late RFIs.
Solution: Pre-task review, mark-ups, and early RFIs. Agree on details before the crew mobilizes.
Example: Many teams see 10–20% productivity swings tied to drawing clarity. A 15-minute pre-task huddle reviewing details pays back the same day.
Equipment and Access
Problem: Shared lifts, dead batteries, long walks.
Solution: Reserve critical equipment by time block. Stage chargers. Request temporary access paths.
Example: Sharing one lift between two trades can cut output by a third during peak hours. Time-blocking from 7–10 AM for your crew stabilizes the rate.
Crew Mix and Sequencing
Problem: Too many or too few people; out-of-sequence work causes rework.
Solution: Right-size the crew to the space and sequence. Split into sub-crews for tight areas.
Example: A 4-person drywall crew in small rooms trips over itself. Two 2-person crews in separate zones often produce more per hour.
Quality and Rework
Problem: Rushing causes punch hits.
Solution: Quality checkpoints at natural breaks (first room, first bay). Fix the template before mass production.
Example: Catching a layout mistake after 50 studs installed is painful. A 10-minute check after the first 20 saves hours later.
Step 5: Price and Schedule Using Your Rates
Rates aren’t just for postmortems—they’re planning tools.
Build From Units
- Estimating: Quantity (units) x HPU x labor rate = labor cost.
- Scheduling: Quantity (units) Ă· UPH Ă· crew size = crew-days.
- Include setup/teardown, mobilization, and learning-curve time for new systems.
Document Assumptions in Your Proposal
Spell out what your rate assumes: access, staging, lift availability, working hours. If conditions change, the rate changes—and so does the price.
With Donizo, you can speak your scope, conditions, and photos into your phone and get a clean, branded proposal out fast. Clients can approve via e-signature, and accepted proposals convert to invoices in one click on paid plans, which helps you keep cash flow aligned with actual progress.
Risk and Float
- Weather-sensitive exterior work: Add contingency days in wet/cold seasons.
- Confined remodels: Plan a slower rate or smaller crews.
- New materials or systems: Start with conservative rates and tighten after the first bay/room.
Example
You’re bidding 8,000 sq ft of Level 4 drywall finish. Your validated rate is 180–220 sq ft per labor-hour in open areas. The plan shows many soffits and reveals; you pick 180 and document “architectural details reduce output.” At 180, that’s 44.4 labor-hours. With a 3-person crew (24 hours per day), that’s just under 2 crew-days, plus setup and cleanup. The proposal states access, staging, and working hours—so if the GC changes any of those, you’ve got a clear basis for a change order.
Frequently Asked Questions
What’s the simplest way to measure productivity without software?
Use daily tallies: units installed and total labor-hours, plus a note on conditions. A whiteboard photo at day’s end works. Consistency beats complexity.
How often should I update my productivity rates?
Review monthly during active projects and after each job closes. Update when crew mix, tools, or typical job conditions change. Seasonal exterior work may need separate summer/winter rates.
How do I handle mixed crews or multiple tasks in a day?
Track hours per task. If that’s too detailed, at least note the dominant task and any significant secondary task. For mixed tasks, log units for each where possible. Over time you’ll separate rates cleanly.
What if conditions change mid-project?
Note the change (e.g., lift removed, work hours shortened) and start a new rate line for that period. Update the schedule and, if your proposal documented assumptions, issue a change order reflecting the new productivity basis.
Can small shops benefit from tracking rates?
Absolutely. In general, small shops see the biggest gains because one bottleneck (material runs, unclear details) affects a large share of total hours. A few minutes of daily tracking can recover hours each week.
Conclusion
When you define units, log daily production, and fix bottlenecks fast, schedules tighten and margins hold. Start with simple tallies, build baselines from your own work, and price with clear assumptions. If you need to turn field notes into a professional proposal quickly, speak it into Donizo and send it with e-signature. Once approved, convert it to an invoice in one click on paid plans. That keeps your paperwork as efficient as your crew—and that’s real productivity.