Turn handover chaos into cash. A simple 48âhour punchâlist process to close jobs, reduce disputes, apply correct VAT, and get paidâpowered by Donizo.
[August 2025 Update] More homeowners are bundling energy upgrades with general renovation to secure financing. Multiâtrade jobs mean more moving parts at handover. If you donât tighten your snag process, you wait longer for the final payment.
This is a simple fieldâtested plan to finish cleanly, avoid disputes, apply the right French VAT, and get the balance in fast.
Why handovers drag (and cost you)
Verbal agreements: âWeâll fix that next weekâ turns into 3 weeks and no payment.
Mixed VAT: energy items at 5.5%, renovation at 10%, a few supplies at 20%âinvoice confusion stalls payment.
No paper trail: you send photos, client replies on WhatsApp, nobody signs anything.
Small misses: a silicone bead, a paint touchâupâenough for the client to hold back the full balance.
The 48âhour snag plan
Think of it like a miniâproject inside your project. Tight, clear, signed.
Step 1 â Preâwalk prep (the day before)
Clean the site. Dust and mess create âfake defects.â
Test everything: flows, pressure, electric, venting, doors, windows.
Make a quick selfâsnag list so you know whatâs left.
Send the appointment message:
Subject: Handover walkâthrough â tomorrow at 17:30
Hello [Client],
I propose a 30âminute walkâthrough tomorrow at 17:30 to verify the works and list any minor snags. Weâll agree whatâs left, set dates, and confirm acceptance. Ok for you?
[Your Name]
Step 2 â The walkâthrough (Day 0)
Walk clockwise through each room, top to bottom.
Write snags in one list. Photos help but keep one single list.
Ditch the paperwork and reclaim your time with Donizo.
Contractors across Europe trust Donizo to handle their quotes and invoices while they focus on what they do best: their craft.
For each snag, note: location, what, how to fix, deadline.
Example line items:
Kitchen â Base unit left â Door slightly misaligned â Adjust hinges â By Thu 05/09
Bathroom â Silicone at tub edge â Add bead â By Wed 04/09
Agree the list with the client on the spot. No arguing, just facts.
Step 3 â Acceptance + plan (still Day 0)
Get two signatures: 1) acceptance of works with snags listed, 2) agreement on snag deadlines.
Use wording like this:
Acceptance with snags (France):
The client accepts the works on [date], with the following snags to be resolved by the stated deadlines. The balance becomes due upon acceptance, with any retention limited to the value of unresolved snags.
Set your invoice due date based on acceptance (common for private homeowners).
Around 10 minutes of admin here saves weeks of chasing later.
At this point, centralize the list, photos, and acceptance in one place. Create the snag list by voice, get the client to eâsign, and queue the balance invoice in Donizo. Youâll have one clean record instead of scattered messages.
Step 4 â 24âhour fixes (Day 1)
Do the quick wins first: silicone, hinge tweak, plate, paint touch.
Update the list as you go. Tick done, add photo proof.
If something needs a part, message the client with the ETA.
Client can be on site or remote. Show photos for each snag ticked.
Get a short âsnags clearedâ signâoff.
Snags cleared â confirmation
Client confirms all snag items completed on [date]. Retention (if any) is now due.
VAT without headaches at the finish line
10%: most renovation on existing dwellings.
5.5%: energy improvement works and related items.
20%: new build and some standalone supplies/equipment.
Tips to avoid invoice disputes:
Separate items by VAT rate on the invoice. Donât mix.
If you added a lastâminute supply not eligible for reduced VAT, put it on a 20% line.
Keep the client renovation/energy attestation with your acceptance file.
Invoice note example:
Invoice note:
Lines 1â5 at 10% (existing dwelling renovation)
Line 6 at 5.5% (energy improvement)
Line 7 at 20% (standalone supply)
Need clean VAT lines and a paper trail that even a banker understands? Generate the invoice with correct French VAT (20%, 10%, 5.5%), attach the signed acceptance, and log payments automatically in Donizo. No more âwhereâs that document?â on payday.
Followâup that gets money in (without being pushy)
Use a simple, planned schedule. Save it once, reuse forever.
Day 0 (after acceptance):
Invoice sent + short SMS: âInvoice sent. Thank you for your trust. Due on [date].â
Day +5:
Gentle reminder: âHello, just checking you received the invoice and acceptance docs. All ok?â
Day +10:
Clear ask: âHello, balance is due on [date]. Here is the payment link/IBAN. Tell me if you need anything.â
Day +15:
Firm but friendly: âHello, balance now overdue. Please arrange payment today to avoid late fees.â
Track whoâs paid, whoâs late, and whatâs still owed by job.
You donât need 5 different apps. Quotes by voice, proposals, invoices with proper VAT, payment tracking, project status, and client notesâdo it endâtoâend in Donizo. Less admin, more work done.
Quick checklist you can print
Handover booked 24h ahead
Site cleaned and selfâsnagged
One written snag list (location, fix, deadline)
Acceptance signed with snags attached
VAT lines split (5.5% / 10% / 20%)
Balance invoice sent same day
24âhour quick fixes done and logged
Snag clearance signed
Followâup schedule running
Final word
Youâll never get rid of every snag. The goal is simple: one list, one signature, one invoice. Keep it tight, keep it moving, get paid.
Ready to try a faster finish? Create your next snag list, acceptance, and invoice in minutes with Donizo.